May 12th 2021
Piling commences for Block D
May 10th 2021
Block C - Steel frame will be completed this week.
Block B - Partitions installed to levels 9, 8, 7 and 6.
Block B - Windows installed to levels 6 and 7.
Block C - Metal decking to the 1st, 2nd, 3rd, 4th, 5th and 6th floors April 8th 2021
Window installation nears completion on floors 8 and 9.
Block C steel frame erection works ongoing Block C steel frame erection works ongoing March 18th 2021
Block B window installation commences
Block C steel frame arrives Thursday 18th March
March 10th 2021
Block C steel frame delivery scheduled for Thursday 18th March March 5th 2021
Muck shift continues to completion during March 2021
March 4th 2021
Block B internal drainage works underway March 3rd 2021
Block C cropping piles underway
February 19th 2021
Block B internal blockwork commences 22.02.21
Block B window installation due to commence 08.03.21
Block B - Glassroc x weather boarding commences 22.02.21
Block B external perimeter drainage works ongoing.
Block C steel frame fabrication underway.
Block C piling work continues.
Block B roof installation well underway and due for completion in 6 weeks.
Block B external SFS expected to be completed by end of February 2021.
February 17th 2021
Main earth shift underway across entire site.
Mast climbers and hoist installed on Block B with works progressing well into February.
January 19th 2021
Sourced Development Group announce contract award to Nationwide Management Services Group across all North West sites.