May 10th 2021
Steel frame completed - Concrete floor installation commences. April 8th 2021
Under slab drainage works ongoing Metal deck and concrete floors - work commences Steel frame erection complete March 8th 2021
Steel frame is delivered to site and assembly has commenced March 5th 2021
Concrete foundations poured including lift pit completion expected w/c 08.03.21 February 19th 2021
Steel frame and pre-cast stairs due for installation 01.03.21 Site contractor has dug and poured the mass fill for 21 out of 25 of the perimeter foundations January 25th 2021
Sourced Development Group ground works on Derby Court Liverpool are commencing with steel frame due for delivery in early March 2021. January 19th 2021
Sourced Development Group announce contract award to Nationwide Management Services Group across all North West sites.
Comentários